March 1st
Launch Direct Project, begin Phase I (specification)
March-April
Recruit Direct Project Implementation Group
March-May
Solicit and refine User Stories
May 6th
Direct Project Face to face meeting
April 1st
Direct Project Implementation Group defined
April
Define first draft of Specifications and Service Descriptions
May 1st
Close User Stories under consideration, publish first draft of Specifications and Service Descriptions, begin Phase II (implementation)
May-October
Implement and refine Specifications and Service Descriptions
June 11th
Direct Project Face to face meeting
September 27th
Direct Project Face to face meeting
November 1st
Begin Phase III of Direct Project (expansion)

Yes, we know this is aggressive.